FUSE · Issue #3 · The Undelivered Electricity, Part 2
BEFORE WE START — FIVE THINGS, ONE LINE EACH
9.0 GW of large load ERCOT has actually approved to energize — against 474 GW that has asked.
474 gigawatts have asked Texas for a grid connection. ERCOT has approved nine.
Every AI-power thesis this year opens with the queue’s headline number — 474 GW — and leaves out the one that matters. ERCOT’s own status report puts “Approved to Energize” at 9,042 MW. The observed peak draw from that approved load was under 4 GW. The queue is 1,800 projects, about 90% of them data centers, and the state has just ordered an audit of 250–300 of them because, in ERCOT’s words, many “lack elements such as financing and companies that have agreed to lease server space.” If you’re pricing a power stock, a turbine maker, or a transformer supplier off 474, you’re pricing a wish list.
That doesn’t mean the shortage is fake. It means the shortage is somewhere else than the headline says — and that’s where the money is.
What “Batch Zero” says out loud
ERCOT’s first cohort under the new large-load process, before the pause

Out of 1,800 projects, ERCOT could name six that plausibly energize in the first quarter of next year. Six.
WHY THE QUEUE LIES
Filing is free. There’s no cost to reserve a place in line, so developers file everywhere, size everything for the biggest possible build, and let the grid operator sort it out. Utilities, who plan on these numbers, told the state their forecasts were “bloated by speculative projects.” The governor’s audit is the first attempt to make the queue pay for its own claims: on-site generation, water, tax breaks, and whether anyone has actually signed to lease the servers.
So the queue overstates demand. But here’s the part that keeps the shortage real: the demand that is real isn’t waiting in it. Stargate Abilene has 421 MW running on its own gas turbines with five more under construction. Fermi is building 11 GW of its own generation in Amarillo. Chevron is building its first power plant in its history. Behind-the-meter capacity in Texas is 2 GW live against 90 GW planned. The serious money already concluded what this issue is telling you — the queue won’t deliver — and routed around it.
That’s the trade. Not “will the grid connect 474 GW.” It won’t. The trade is what it costs to not need the grid.
TWO WAYS THIS RESOLVES
We're in B until we see an A tell.